Irish Sunday Times 14th Oct 2018 download PDF below



|
Top 10 Ireland, CERTIFIED PASSIVE HOUSE with A1 BER

ED Bungalow, near Bunclody, Co. Wexford
This Bungalow is a Certified Passive House with BER Rating of A1,
6th Certified Passive in Co Wexford and top 30 of dwellings with a A1 BER
of 674,698 houses tested by 1st Feb 2017 in Ireland.
This is a Split level House with Living room an Kitchen/Diner three steps below rest of House.
The bedroom wing is to the left of main entrance.
The terrace is south facing. Below are design 3D views.

newest photos on top
Passive House + magazine, photo shoot 06.05.2018
Bungalow settling nicely, two years on.
Photos 08.01.2016
Skirting and architraves in, Kitchen in Progress.
Photos 22.12.2015
Timber and tiled floors in.
Photos 27.11.2015
Heating on and Blower test 2 done.
Photos 06.11.2015
Ceiling insulation in progress 450mm quilts.
Photos 20.10.2015
Floor insulation in , underfloor heating pipes in, fast floor screed complete.
Photos 07.10.2015
Floor insulation nearly finished.
Photos 28.09.2015
Floor insulation on site and outsided concrete paths finished.
Photos 09.09.2015
Greenbuild doorblower testing day with loads of smoke.
Photos 06.08.2015
Window fitting finished airtighness taping in final stages, Wincon test to see if there are any leakage.
Photos 30.07.2015
Windows arrived, fitting started. Aluclad windows charcoal outside, cream inside.
click thumbnail to see full photo click right on pic for next pic - click left on pic for previous pic
Photos 17.07.2015
Insulating Window cill and Head.
Photos 14.07.2015
MHRV ducting installation in progress. Suspended ceiling as well.
Photos 02.07.2015
Electrics chasing finished. Airtightness taping to begin.
Photos 15.06.2015
Views from drive way. Getting ready for base coat of plaster outside.
Photos 05.06.2015
Slating completed, Black PVC Facia cladding in progress.
Photos 27.05.2015
Slating in progress, cill brackets too. True Windows ordered.
Photos 20.05.2015
Slating in progress, cill brackets too.
Photos 14.05.2015
Roof membrance on ready for slates.
Photos 29.04.2015
Roof trusses nearing completion.
Photos 24.04.2015
Roof trusses over half way.
Photos 17.04.2015
Roof trusses starting.
Photos 10.04.2015
Interior blockwork nearly completed.
Photos 27.03.2015
Interior blockwork started.
Photos 16.03.2015
Nearly all exterior blockwork done.
Photos 10.03.2015
Block work in full swing
Photos 27.02.2015
Slab down block work started
Photos 18.02.2015
Weather ok, radon barrior down.
Photos 12.02.2015 First batch of photos.
Setting out and rising walls.
click thumbnail to see full
photo
click right on pic for next pic - click left on pic for previous
pic